Transportation

I-77 / Cornelius Road interchange (Exit 38)

Funded

NCDOT’s January 2026 program includes the Cornelius Road interchange with projected right-of-way and utilities in fiscal 2028, and construction in fiscal 2031.

At a glance

Status
FundedFunded means programmed phase allocations in the state program, not current construction or a delivery guarantee.
Location
I-77 at Cornelius Road, northern Mooresville
What is planned / being built
A future I-77 interchange at Cornelius Road, known as Exit 38.
Latest verified development
Town GIS lists I-5962 in preliminary design, with a September 2031 construction field and an approximate three-year duration. Its record was last edited March 25, 2026. [11]Verified fact · Evidence March 25, 2026
What to watch next
Projected right-of-way phase
Last checked
October 6, 2026Source review date; not a new construction event.

What this record covers

New interchange at existing Cornelius Road grade separation; do not conflate with I-77 Exit 36.

WHAT TO WATCH NEXT

Projected right-of-way phase

FY 2028 [3]

Timing remains subject to source confirmation and delivery conditions.

What remains uncertain

  • Check subsequent STIP amendments and the current design record before treating January dates as unchanged.
  • No construction commencement or opening date is established here.
  • Town GIS approximate cost ($68.83m) differs from January STIP funds needed ($66.59m); reconcile before treating either as the current complete budget.

What is documented

  • Verified fact

    I-5962 would upgrade the existing grade separation to an interchange. [3]

    Documented statement; verification does not guarantee delivery. Evidence date: January 2026.

  • Verified fact

    The January program schedules right-of-way and utilities for FY2028 and construction for FY2031. These are projected starts, not an opening date. [3]

    Documented statement; verification does not guarantee delivery. Evidence date: January 2026.

  • Verified fact

    Town GIS lists I-5962 in preliminary design, with a September 2031 construction field and an approximate three-year duration. Its record was last edited March 25, 2026. [11]

    Planning fields are not an awarded construction contract or a confirmed opening schedule. Do not calculate an opening date. Evidence date: March 25, 2026.

  • Verified fact

    January STIP lists $66.59 million in total funds needed; the town GIS approximate cost is $68.83 million. No reconciled current project budget is adopted. [3] [11]

    Different editions/bases require agency clarification.

Amounts & scale

  • Stip total funds needed: $66,590,000 · estimate [3]

    January STIP: $7m right-of-way, $630k utilities, $58.96m construction; not reconciled with town GIS approximate cost. Evidence date: January 2026.

Targets & projected dates

  • Projected right-of-way and utilities start: FY 2028 · Agency projection [3]
  • Projected construction start: FY 2031 · Agency projection [3]

Why it matters

Reasonable inference

Future highway access could change circulation around northern Mooresville. Timing and parcel access remain critical unknowns. [3]

Sources & evidence

  1. NCDOT — 2026–2035 STIP, January 2026 edition

    PDF pages 205, 209 and 210 (printed 12-6, 12-10 and 12-11) · Source date: January 2026 · Checked: October 6, 2026

    Fiscal-year starts are projected schedules, not opening dates.

  2. Town of Mooresville GIS — Active Transportation Projects: town point records

    OBJECTID 69 U-6239, last edited May 7, 2026; OBJECTID 44 I-5962, last edited March 25, 2026 · Source date: not shown · Checked: October 6, 2026

    Selected attributes retained in source-checks. Feature edit dates describe data revisions, not construction events. Null DateCompleted is not proof that a road is still closed. ApproxTime/ConstDate fields are projections and may be stale.